Safari Circuits, Inc. v. Chicago School Reform Board of Trustees

February 21, 2007

SAFARI CIRCUITS, INC., PLAINTIFF,
v.
CHICAGO SCHOOL REFORM BOARD OF TRUSTEES, ET AL., DEFENDANTS.



The opinion of the court was delivered by: Milton I. Shadur Senior United States District Judge

MEMORANDUM OPINION AND ORDER

Safari Circuits, Inc. ("Safari") brings a breach of contract claim against the Chicago Board of Education ("Board")in this diversity action. Safari was a subcontractor to Systems Concepts, Inc. ("Systems") under a contract between Systems and Board ("Systems Contract") that called for Systems to provide and install audiovisual equipment for Board facilities ("Installation Project"). Safari claims that as a subcontractor on the Installation Project it was a third-party beneficiary of the Systems Contract and that Board breached that agreement when it failed to obtain a payment bond from Systems for the benefit of any subcontractors as required by the Illinois Public Construction Bond Act ("Bond Act," 30 ILCS 550/0.01 to 550/3).*fn1

Safari and Board have now brought cross-motions for summary judgment under Fed.R.Civ.P. ("Rule") 56. As this opinion explains, the Bond Act does not apply because the Systems Contract was not a contract for "public work." Hence no payment bond was required, so that Safari's motion is denied and Board's motion is granted.

Standard of Review

Under familiar Rule 56 principles, a movant for summary judgment bears the burden of establishing the absence of any genuine issue of material fact (Celotex Corp. v. Catrett, 477 U.S. 317, 322-23 (1986)). For that purpose courts consider the evidentiary record in the light most favorable to nonmovants and draw all reasonable inferences in their favor (Lesch v. Crown Cork & Seal Co., 282 F.3d 467, 471 (7th Cir. 2002)). But to avoid summary judgment a nonmovant "must produce more than a scintilla of evidence to support his position" that a genuine issue of material fact exists (Pugh v. City of Attica, 259 F.3d 619, 625 (7th Cir. 2001)). Ultimately summary judgment is appropriate only if a reasonable jury could not return a verdict for the nonmovant (Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)).

One more complexity is added here, where cross-motions for summary judgment are involved. In this case those same principles require the adoption of a dual perspective that this Court has sometimes referred to as Janus-like: As to each motion the nonmovant's version of any disputed facts must be credited.*fn2

Finally, as a federal court sitting in diversity, this Court is charged with applying state law --- in this instance Illinois law --- to resolve all substantive questions (M.T. Bonk Co. v. Milton Bradley Co., 945 F.2d 1404, 1407 (7th Cir. 1991)). What follows then, is (1) a summary of the facts that either are undisputed or are viewed in the light most favorable to Safari (as the party that has ultimately come up short), followed by (2) an application of Illinois substantive law to those facts.

Background

After issuing a May 2000 request for proposals, Board selected Systems to provide the Installation Project (S. St. ¶¶6-7). Systems was to design, deliver and install a multimillion dollar digital audiovisual system to allow Board to store digital media content on servers at its Central Office and to allow teachers then to download that content directly to computers in their classrooms at some 182 different schools (id. ¶¶8, 58-63). That system would eliminate the teachers' need to check out and transport physical equipment such as DVD players and DVDs from a central library (id.). As this brief summary indicates, that project was no small endeavor.

In October 2003 Safari agreed to provide Systems with various audiovisual network products and services required for the Installation Project (S. St. ¶8). To meet Board's specific requirements Safari spent months in specially designing and manufacturing some 200 hardware components known as "ASC300s," "multiplexers" or "multiplexer interfaces," as well as some other equipment to be installed at the Central Office and the various schools (id. ¶¶22-27). Systems was also required to program and configure all of the necessary computer hardware (id. ¶34).

Before undertaking the installation itself, Systems personnel visited each site to assess whether the school's facilities were ready to accept and interface with the equipment (S. St. ¶¶37-38). For example, before some of the schools would be ready work was required to install additional wall outlets. All of that work, however, was performed by Board personnel and not by Systems or Safari as part of the Installation Project (B. St. ¶39).*fn3

Once the time for installation came, Systems and Safari installed "an interconnected series of eight computer servers, four DVDNCR units, various audio and video output devices, various cables, and four ASC3000s" at the Central Office ("Central Office Equipment")(S. St. ¶29). That Central Office Equipment was then connected to Board's wide-area network ("Network") by a series of 36-foot patch cables that were also attached to a metal rack running along the ceiling to keep them tidy and out of the way (id. ¶33). At each of the schools Systems installed a server, a DVDNCR unit, an ASC3000, a monitor, an uninterruptible power supply and associated cables to connect those components (id. ¶35.) Most of that equipment was mounted onto large racks by screws or otherwise, and the racks were in turn bolted to the floor to prevent tipping (id. ¶¶51-52). In about a dozen of the 182 schools involved, Systems needed to install new racks that it provided and assembled for the Installation Project (id. ¶¶55-57).

All of that installation work at the Central Office and some 182 schools took weeks to accomplish (S. St. ¶45). Then after installation a Safari employee visited each of the schools to connect the equipment to the Schools' Networks with patch cables and to test for the proper functioning of the equipment, including checking the connections between computers and servers in 8,100 classrooms (id. ¶¶46, 49). Safari then conducted training sessions on the use of the new equipment for Board personnel (id. ¶47).

Even though Systems received payment for its work on the Installation Project, it became insolvent and has not in turn compensated Safari for its work (S. St. ΒΆ16). This Court has already entered judgment against Systems in Safari's favor in the amount of $691,404.91, but the uncertainty of recovery on that judgment in light of Systems' financial condition (id.) understandably leads Safari to look to Board. And because Board did not require Systems to post a payment bond as part of the Systems Contract for the benefit of subcontractors on the Installation Project (id. ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.