Trucking Co., Inc. v. Envirocon

October 13, 2006

TRUCKING COMPANY, INC., PLAINTIFF,
v.
ENVIROCON, INC. AND BRIAN BELL, DEFENDANTS.



The opinion of the court was delivered by: Stiehl, District Judge

MEMORANDUM & ORDER

Before the Court is plaintiff's motion for summary judgment (Doc. 41), to which defendants have responded (Doc. 42).

BACKGROUND

Plaintiff originally filed its complaint in state court. Defendants removed the matter to federal court. Plaintiff is an Illinois Corporation involved in trucking and hauling. Plaintiff executed a contract with defendant Envirocon, Inc. relating to a job in Granite City, Illinois. (Doc. 2, Ex. A). In its complaint, plaintiff alleges that Envirocon breached this contract by failing to remit to plaintiff funds owed for work done, failing to purchase various loads called for in the contract, and/or failing to use plaintiff's personnel and equipment as required by the contract. (Doc. 2, ¶ 5). Plaintiff's complaint further alleges that defendant Brian Bell was the project director for Envirocon. Count II of the complaint alleges that Bell interfered with plaintiff's business expectancy and caused Envirocon to breach its contract with plaintiff.

In his answer, Bell claims that the relief sought by plaintiff is barred by the following affirmative defenses: one, that the complaint fails to state a claim upon which relief can be granted; two, because plaintiff has failed to mitigate its damages, if any; three, defendants did not legally or proximately cause plaintiff's alleged injury; four, the doctrine of accord and satisfaction; five, "the Subcontract Agreement expressly provides that final payment to Plaintiff would be based on a determination of final topographically surveyed quantities of actual materials placed, less progress payments made by Envirocon;" six, Bell is not a "third party" as required in a successful claim of tortious interference; seven, Bell is entitled to immunity as an employee of Envirocon; and eight, waiver and/or estoppel. Envirocon also asserted several affirmative defenses in its Answer.

Plaintiff now moves for summary judgment against defendant Envirocon on all counts, and against both defendants on their First, Second and Fourth Affirmative Defenses.*fn1

A. The case in chief against Envirocon.

Plaintiff seeks summary judgment in its favor on all Counts relating to defendant Envirocon.

STANDARD

Summary judgment is appropriate "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Fed. R. Civ. P. 56(c). The moving party initially bears the burden to demonstrate an absence of genuine issues of material fact, indicating judgment should be granted as a matter of law. See, Lindemann v. Mobil Oil Corp., 141 F.3d 290, 294 (7th Cir. 1998) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986)). Once a motion for summary judgment has been made and properly supported, however, the non-movant has the burden of setting forth specific facts showing the existence of a genuine issue for trial. See, id. In determining whether a genuine issue of material fact exists, the Court construes all facts in the light most favorable to the nonmoving party and draws all reasonable and justifiable inferences in that party's favor. Hedberg v. Indiana Bell Tel. Co., 47 F.3d 928, 931 (7th Cir. 1995).

ANALYSIS

Plaintiff seeks summary judgment against Envirocon "on all counts;" however, only Count 1 of plaintiff's complaint is against Envirocon. In Count 1, plaintiff alleges that defendant Envirocon breached its contract with defendant by failing to remit to plaintiff funds owed for work done, failing to purchase various loads called for in the contract, and/or failing to use plaintiff's personnel and equipment, which were contracted for use. (Doc. 2, ¶ 5). In support of its motion, plaintiff asserts many "uncontroverted" facts that it purports show that Envirocon breached its duty. In its response, Envirocon also asserts many "uncontroverted" facts in its defense. The Court finds neither argument to be persuasive. When viewing the facts in the light most favorable to the nonmoving party, summary judgment is not appropriate on this Count. Genuine issues of material fact remain as to whether Envirocon breached the contract or plaintiff released Envirocon from its obligations. Plaintiff's motion for summary judgment as to Count 1 against Envirocon is, therefore, DENIED.

B. The Affirmative Defenses

Plaintiff seeks summary judgment in its favor on defendants' First, Second, and Fourth Affirmative Defenses. In its argument, plaintiff refers to no facts outside the pleadings when attacking defendants' First and Second Affirmative Defenses. Of course, this is really an attack on the pleadings, and not an attack on the merits of defendant's claims; therefore, the Court could not possibly grant summary judgment on the affirmative defenses. The Court will, however, consider plaintiff's motion ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.