Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.

Union Boiler Works Inc. v. Caldera

October 09, 1998

UNION BOILER WORKS, INC., APPELLANT,
v.
LOUIS CALDERA, SECRETARY OF THE ARMY, APPELLEE.



Before: Rich, Newman, and Lourie, Circuit Judges.

The opinion of the court was delivered by: Lourie, Circuit Judge.

Appealed from: Armed Services Board of Contract Appeals

Union Boiler Works, Inc. ("UBW") appeals from the final decision of the Armed Services Board of Contract Appeals denying its claim for an equitable adjustment for the costs associated with the Army's use of its temporary boiler. See In re Union Boiler Works, Inc., ASBCA No. 49131, 96-2 BC ¶ 28,331 (May 6, 1997) ("UBW II"), 97-2 BC ¶ 29,178 (Aug. 6, 1997) ("UBW III"). Because the Board erred in its determination that UBW could not recover "hook-up and start-up costs," but did not err in its determination that UBW could not recover damages for its lost opportunity to rent the boiler, we affirm-in-part, reverse-in-part, and remand.

BACKGROUND

UBW contracted with the Army to renovate three boilers at the Army's Aberdeen Proving Ground in Maryland. The contract required in relevant part that UBW furnish a temporary boiler at its expense if UBW did not finish the renovation of boiler 1 by October 18, 1989. *fn1

On September 26, 1989, the Army requested that UBW replace the insulation on boilers 1 and 2. UBW complied, and accordingly missed the boiler 1 due date and installed its fully-depreciated temporary boiler in lieu of boiler 1. UBW claimed that the insulation work and its provision of the temporary boiler constituted compensable changes in the contract and demanded an equitable adjustment. The Board, in a decision not appealed here, agreed that the insulation work constituted a compensable change. See In re Union Boiler Works, Inc., ASBCA Nos. 41856, -58, 95-1 BC ¶ 27,304 (Nov. 15, 1994) ("UBW I"). The Board further determined that the insulation work should have taken 90 days and therefore that UBW was obligated to supply the temporary boiler at its own expense no sooner than January 16, 1990, i.e., 90 days after the original October 18th due date. See UBW I, slip op. at 11. Thus, the Board sustained UBW's temporary boiler claim "to this extent," and remanded the case to determine the amount of compensation due to UBW. See id.

The Board's subsequent decisions following the remand focused on UBW's entitlement to compensation for two alleged consequences of its provision of the temporary boiler: the "hook-up and start-up" costs and lost opportunity to rent. The Board ruled on cross-motions for summary judgment that UBW was not entitled to recover the hook-up and start-up costs for the temporary boiler because it did not finish the renovation of boiler 1 until March 27th, well after the extended January 16th deadline, and thus it would have had to have supplied the temporary boiler even absent the interruption caused by the insulation work. See UBW II, slip op. at 4-5. In a subsequent decision, the Board ruled as a matter of law that 48 C.F.R. § 31.205-11(l) (1989) barred UBW from recovering damages for its lost opportunity to rent the temporary boiler. Accordingly, the Board disregarded as irrelevant UBW's evidence that $4,500/month was a reasonable rental rate for its temporary boiler. UBW III, slip op. at 6-7, 9. Moreover, the Board found that the parties did not attempt on remand to agree to a "reasonable charge" under this provision and that no evidence existed in the record relevant to that issue.

UBW appealed to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10) (1994).

Discussion

The standard under which we review a decision of the Board is dictated by the Contract Disputes Act, which provides in relevant part that:

"the decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence." 41 U.S.C. § 609(b) (1994).

Notwithstanding this lack of deference concerning questions of law, "legal interpretations by tribunals having expertise are helpful to us, even if not compelling." Erickson Air Crane Co. v. United States, 731 F.2d 810, 814 (Fed. Cir. 1984).

UBW argues that the Board specifically found that it "would have completed repairs on boiler 1 by [October 18, 1989] but for the additional 90 days reasonably required" to perform the insulation work. UBW I, slip op. at 11. Accordingly, UBW continues, it would not have had to install the temporary boiler had it not been for the insulation work, and therefore it is entitled to recover its hook-up and start-up costs. UBW opines that its completion of the renovation of boiler 1 beyond the 90-day extension does not affect this Conclusion. Moreover, UBW argues that it is entitled to recover damages for its lost opportunity to rent its temporary boiler during the 90-day extension period, and it cites 48 C.F.R. § 31.205-36 (1989) in support of its position.

The Army responds that the Board did not err in denying "hook-up and start-up costs" and damages for the lost opportunity to rent the boiler. As to the hook-up and start-up costs, the Army argues that UBW's delay in completing the renovation of boiler 1 shows that UBW would not have met the original due date even if the Army had not requested the insulation work, and therefore that UBW would have incurred these costs regardless. As to the ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.