Simmons v. Union Electric Co.

OPINION FILED NOVEMBER 30, 1984.

EDWARD SIMMONS, APPELLEE,

v.

UNION ELECTRIC COMPANY, APPELLEE (SACHS ELECTRIC COMPANY, APPELLANT).



Appeal from the Appellate Court for the Fifth District; heard in that court on appeal from the Circuit Court of St. Clair County, the Hon. Thomas M. Daley, Judge, presiding.

JUSTICE SIMON DELIVERED THE OPINION OF THE COURT:

We are called upon in this appeal to decide (1) whether the Structural Work Act (Ill. Rev. Stat. 1981, ch. 48, par. 60 et seq.) applies to the plaintiff's claims against the defendant, (2) whether the principles of comparative fault are applicable to the plaintiff, a workman who brought a claim under the Structural Work Act (the Act), in view of this court's decision in Coney v. J.L.G. Industries, Inc. (1983), 97 Ill.2d 104, a question left unresolved by our decision in Doyle v. Rhodes (1984), 101 Ill.2d 1, 17, and (3) whether the defendant is entitled to indemnity from a third-party defendant.

The plaintiff, Edward Simmons, sought recovery against the defendant, Union Electric Company (Union Electric), in the circuit court of St. Clair County for injuries he received while working as an electrical repairman for Sachs Electric Company (Sachs) at Union Electric's power plant in Cahokia, Illinois, a plant which had been shut down. Union Electric had no personnel in this plant except for employees who inspected the property from time to time. Sachs had entered into contracts with Union Electric to install and maintain electrical power to the Cahokia plant. Simmons and another Sachs' employee (since deceased) were sent to the Cahokia plant by Sachs, at the request of Union Electric, because of flooded conditions at the plant. After arriving at the plant, they discovered that a sump pump had become inoperative, resulting in flood waters remaining in an ash pit in which the pump was housed. Simmons, while descending into the ash pit on a permanently affixed ladder which had become covered with oil from the flood waters, slipped, fell into the ash pit, and sustained injuries.

Oil on the ladder was apparently not unusual at the Cahokia plant. Previous flooding at the plant had left a similar residue which had, at least on one occasion, required Union Electric to hire an outside contractor to clean the oily surfaces. Evidence submitted at trial also establishes that Sachs had knowledge of the oily conditions in the plant after previous flooding had occurred. According to the terms of its contract with Union Electric, Sachs was responsible for "all appropriate safety precautions necessary or advisable for the prevention of accidents" when Sachs' employees were working at the Cahokia site.

Union Electric filed a third-party complaint against Sachs seeking either contractual or common law indemnity. In the alternative, Union Electric sought contribution from Sachs, which in turn filed a counterclaim against Simmons seeking indemnity or contribution, other than the contribution provided for by section 5(b) of the Workers' Compensation Act (Ill. Rev. Stat. 1981, ch. 48, par. 138.5(b)).

After a bench trial, the circuit judge, without explanation, entered judgments under the Structural Work Act for plaintiff in the amount of $219,000 against Union Electric and in favor of Sachs on Union Electric's third-party complaint. The appellate court affirmed plaintiff's judgment against Union Electric, but it reversed the judgment in favor of Sachs on Union Electric's complaint for indemnity and entered judgment in favor of Union Electric (121 Ill. App.3d 743). The appellate court also held for Simmons on Sachs' counterclaim for contribution or indemnity. We granted Sachs' petition for leave to appeal (87 Ill.2d R. 315(a)) and resolve questions not originally contained in that petition, but briefed and argued by another party, pursuant to our power to resolve issues warranted by the record (87 Ill.2d R. 318(a)).

I. APPLICATION OF THE STRUCTURAL WORK ACT TO UNION ELECTRIC

Union Electric first argues that the Act was improperly invoked. Section 9 of the Act provides:

"Any owner, contractor, sub-contractor, foreman or other person having charge of the erection, construction, repairing, alteration, removal or painting of any building, bridge, viaduct or other structure within the provisions of this act, shall comply with all the terms thereof * * *.

For any injury to person or property, occasioned by any wilful violations of this Act, or wilful failure to comply with any of its provisions, a right of action shall accrue to the party injured * * *." (Ill. Rev. Stat. 1981, ch. 48, par. 69.)

Union Electric contends that it did not "have charge of" the plaintiff's work, the work performed was not on a "structure" and no "wilful" violation occurred, and therefore both the circuit and appellate courts erred when they held that Union Electric had violated the Act.

To hold a party accountable under the Act, the court must find that the party had charge of the work in question. Union Electric contends that it had no direct connection with the repair operations and, relying on McGovern v. Standish (1976), 65 Ill.2d 54, it argues that the totality of circumstances in this case is insufficient to find that it had control of the plaintiff's work.

The term "having charge of" "is primarily a factual question." (McGovern v. Standish (1976), 65 Ill.2d 54, 66; see also Voss v. Kingdon & Naven, Inc. (1975), 60 Ill.2d 520, 525.) The factual inquiry involves numerous factors, including those enunciated in Chance v. City of Collinsville (1983), 112 Ill. App.3d 6, 11. The fact that all work performed by Sachs was "subject to inspection and final acceptance" by Union Electric, that Union Electric employees visited the plant regularly while the plant was closed, and that Sachs' employees only entered the Cahokia plant at the request of Union Electric supports the determinations of the circuit and appellate courts that, for the purposes of the Act, ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.