Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Official citation and/or docket number and footnotes (if any) for this case available with purchase.

Learn more about what you receive with purchase of this case.

05/27/66 Saul Ritzenberg Et Al., v. Noland Company

UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT


May 27, 1966

SAUL RITZENBERG ET AL., APPELLANTS

v.

NOLAND COMPANY, INC., APPELLEE 1966.CDC.114 DATE DECIDED: MAY 27, 1966

Wilbur K. Miller, Senior Circuit Judge, and McGowan and Leventhal, Circuit Judges.

UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT

APPELLATE PANEL:

DECISION OF THE COURT DELIVERED BY THE HONORABLE JUDGE MCGOWAN

McGOWAN, Circuit Judge.

This appeal turns upon the proper construction of certain provisions of the District of Columbia laws relating to mechanic's liens. There is no real dispute about the facts, but only about how the statutes are to be read in relation to them. The District Court granted the lienor's motion for summary judgment enforcing the lien. We affirm. I

Appellants are members of a partnership which was formed for the purpose of building an apartment house. The plumbing, heating and electrical work was to be performed by a contractor under an agreement fixing $99,125 as the total price. Appellee furnished materials and supplies to the contractor for use in the project. By April 12, 1963, the contractor owed appellee $6,919.36 (later adjusted to $6,289.50) on account of such materials and supplies; and on that day appellee filed its notice of lien on the building under construction. Despite such notice, appellants thereafter paid the contractor, during the period from April 25 to May 31, a total of $10,015.96 under the contract. The contractor ultimately defaulted, and appellants paid out substantial sums to complete the work. It is agreed that, without including or taking account of the $10,015.96 paid to the contractor after notice of appellee's lien, the total sum of $98,596.54 was expended by appellants in respect of the work called for by the contract. So computed, $528.46 could be regarded as remaining due from appellants under the contract.

It is only this last sum, say appellants, which may, under the governing statute, be made the measure of all lien enforcement. Contrarily, appellee urges that Congress has clearly given it a right to enforce its lien up to the amount of $10,015.96, representing the sums paid to the contractor by appellants after notice of appellee's lien. The District Court agreed with this latter view, and entered judgment of enforcement of the lien in the amount of appellee's claim for $6,289.50. *fn1 II

The provisions which Congress has made for mechanic's liens are set forth in 38 D.C.Code ยงยง 101-126 (1961 ed.). The parties look to different sections of the statute as controlling. Appellants take their comfort from Section 104 which embodies in terms the principle that all liens are subject to the contract between the owner and the contractor, including the total price due under that contract; and are to be satisfied only out of that amount. *fn2 Appellee, on the other hand, rests upon Section 106 which, it contends, affirmatively requires the owner, once on notice of a properly filed lien, to withhold from further payments to the contractor a sum sufficient to satisfy the lien indebtedness, upon pain of seeing the property made answerable at all events, to the extent of such further payments, for the satisfaction of the lien. *fn3

It is certainly true that the purpose and effect of Section 104 are not to expose the owner to liability to the lienors greater than that owed by him to the contractor. See Herrell v. Donovan, 7 App.D.C. 322 (1895); Harper v. Galliher & Huguely, Inc., 29 F.2d 452, 58 App. D.C. 252 (1928), cert. denied, 278 U.S. 657, 49 S. Ct. 185, 73 L. Ed. 565 (1928). And there will be no such exposure unless the owner ignores the explicit commands of Section 106, which is addressed to the making of payments to the contractor by the owner after the latter has been notified that an unpaid supplier claims a lien. The statute says in terms that the owner is to withhold enough from these payments to take care of the claim. The owner's failure to do this makes the lien enforceable to the extent of such payments, whatever may be the degree to which the owner has discharged the obligations running from him to the contractor under the contract. The legislative policy served is to prevent a situation where, as here, appellants own a building containing roughly $6,000 worth of materials and supplies furnished by appellee for which, despite its forehandedness in giving notice to appellants, it has never been paid.

It is not enough for appellants to counter that they in effect have already paid for them once and should not be called upon to do so a second time. The trouble with this is that they made their first payment to the contractor, who did not use it in turn to satisfy his materialmen. And this payment was made at a time when appellants were on notice of appellee's claim. Section 106 seems to us to say quite clearly that the owner does this at his peril. If he chooses to rely on the contractor in this situation to see to it that the money is used to pay the lienor, and the contractor disappoints him in this expectation, then a second payment for the same materials may be the consequence. *fn4 But the bricks are in his building, and the whole theory of mechanic's liens points in the direction of concluding that the equities here reside with the supplier rather than the owner. In any event, we believe that this is how Section 106 was intended to operate in the circumstances before us. *fn5

The judgment is

Affirmed.

CASE RESOLUTION

Affirmed.


Buy This Entire Record For $7.95

Official citation and/or docket number and footnotes (if any) for this case available with purchase.

Learn more about what you receive with purchase of this case.